I-69 Bridge Improvement over Former Railroad Project

DES No. 2002127 (Lead) & 2201184

Anderson, Madison County, Indiana

PROJECT DESCRIPTION

The Indiana Department of Transportation (INDOT) is developing plans for the proposed Interstate 69 (I-69) Bridge Improvement over Former Railroad Project [Des. 2002127 (lead) & 2201184], located along I-69 at INDOT Bridges I69-228-02302 BNBL (NBI number 039270) and I69-228-02302 BSBL (NBI number 039280), approximately 0.58 mile north of State Road (SR) 236 in Madison County, Indiana.

The purpose of the project is to address the current deterioration of the twin bridges and improve the overall condition ratings of the bridges to at least a 7 (good) out of 9 (excellent). The need for this project is evidenced by the deteriorated condition of the I-69 twin bridges.

 

The project proposes to remove the existing twin bridges and replace them with a three-sided concrete culvert (CV I69-228-10815). The new culvert will measure 195 feet long, 20 feet wide, and 14 feet tall. The concrete culvert will accommodate a 10-foot-wide wildlife path and a future 10-foot-wide trail. Headwalls and wingwalls will be constructed at both ends of the culvert and riprap will also be placed at both ends. Following construction of the culvert, the slopes along I-69 will be backfilled to match the existing profile grade of the I-69 roadway. The new typical roadway section of I-69 will include four 12-foot-wide travel lanes (two northbound and two southbound), a 52-foot-wide grassy median, interior 4-foot-wide shoulders, and exterior 11-foot-wide shoulders. All guardrails along I-69 will be replaced in kind.

 

The project will require approximately 2.1 acre of new permanent right-of-way. No temporary right-of-way or relocations are anticipated as part of the project. The maintenance of traffic (MOT) for the project proposes phased lane closures, lane shifts, and median crossovers. Two 11-foot-wide travel lanes in each direction will be maintained along I-69 throughout construction. Access to all properties within an adjacent to the project limits will be maintained throughout construction. The MOT will remain in place for the duration of construction. Project stakeholders including local school corporations(s) and emergency services will be notified of potential closures and/or detours prior to construction. The anticipated start of construction is Summer 2026.

 

The cost associated with this project is approximately $6,842,012 which includes preliminary engineering, right-of-way, and construction with both federal and state funds anticipated to be used.  

PROJECT UPDATES

A Notice of Planned Improvement was published in the The Herald Bulletin newspaper on April 29, 2025 and May 6, 2025. The Federal Highway Administration (FHWA) and INDOT have agreed this project falls within the guidelines of a Categorical Exclusion (CE) Level 2 environmental documents. Preliminary design plans along with the CE document and other project documents are available for review at the links below or at the following in-person location:

 

Anderson Public Library

111 East 12th Street

Anderson, Indiana 46016

 

All interested persons may request a public hearing be held and/or submit comments to the attention of Leigh VanHyfte, of American Structurepoint, Inc, 9025 River Road, Suite 200, Indianapolis, Indiana 46240, (317) 547-5580, or lvanhyfte@structurepoint.com on or before May 14, 2025.

Comment Form

Thanks for submitting!

This form no longer accepts submissions.

Submit all comments by May 14, 2025

CONTACT

Leigh VanHyfte

Senior Environmental Specialist

American Structurepoint, Inc.

317.547.5580

lvanhyfte@structurepoint.com

INDOT.LGO.2.jpg
Structurepoint Logo_Color.png

Check this website for future project updates!